Start with one community and one recurring problem
Choose a recent lot where a crew lost time. Say rough-in moved from Tuesday to Thursday because framing ran late. Purchasing saw the new date, but the plumber’s foreman still had Tuesday on the crew schedule. The crew drove out, found the house wasn’t ready, and had to come back.
Follow the change from the office to the field
We sit down with your superintendent, purchasing team, and the affected trade contractor. Using the lot schedule, messages, and crew assignment, we trace who knew about the change, when they knew it, and which schedule the foreman used to dispatch the crew.
Test one fix on the next few lots
You get a short written summary showing where the update stopped, who needs to receive it, and one change to try. For example, the superintendent could confirm the house is ready with the trade foreman before the crew is dispatched. Count how often crews arrive ready to work on the next few lots to see whether the change helps.